TLDR
The PMP® exam that launched July 9, 2026 has 180 questions in 240 minutes across three domains: People (33%), Process (41%) and Business Environment (26%). Most questions describe a project situation and ask for the best action, so practising with explained scenario questions builds both speed and judgment. Our one-day situational questions workshop ($395, 8 hours) teaches the method in depth.
Pro Tip
Read the last sentence of a long scenario first. It tells you whether the question wants what you should do first, next, or what should have been done earlier, and that one word changes which answer is correct.
PMP® Exam Questions On The July 2026 Exam: What Changed

PMI® launched an updated PMP® exam on July 9, 2026, built on a new examination content outline. The number of questions and the time allowed stayed at 180 questions in 240 minutes, but the balance of the content moved noticeably toward the business environment around each project. New trends such as artificial intelligence and sustainability informed the job analysis behind the exam, and two newer question formats, case-study sets and graphic-based items, now appear alongside traditional multiple choice. Study materials written for the earlier exam do not reflect these changes, so any practice questions you use should be mapped to the 2026 outline.
| PMP® Exam Detail | July 2026 Exam |
|---|---|
| Total questions | 180 (170 scored, 10 unscored pretest questions) |
| Time allowed | 240 minutes |
| Breaks | Two 10-minute breaks, after the case-study section and about midway through the remaining questions |
| People domain | 33% of questions |
| Process domain | 41% of questions |
| Business Environment domain | 26% of questions |
| Approaches covered | Predictive, agile and hybrid |
With roughly 80 seconds per question, pacing matters as much as knowledge. Once you start a break you cannot return to the section you just finished, so review flagged questions before each break. The official PMP® Examination Content Outline lists every task the exam tests, and each of the 12 sample questions in the People, Process and Business Environment sections maps to one of those tasks.
Situational Questions Holding You Back?
Our one-day PMP® Exam Prep: Mastering Situational Exam Questions workshop teaches how to decode scenarios, handle NOT and EXCEPT wording and manage your time. 8 hours, $395.
Types Of PMP® Exam Questions You Will See
The exam mixes several question formats, and knowing how each one works keeps you from losing time on the mechanics during the test. Most items are still single-answer multiple choice built around a short scenario. The case-study format groups several questions around one detailed project description, so you read the context once and answer a sequence of related questions. Graphic-based items ask you to interpret a chart, table or diagram before choosing an answer.
| PMP® Question Type | How It Works |
|---|---|
| Multiple choice | A scenario with four options and one best answer |
| Multiple response | Choose two or more correct answers; the question states how many |
| Case or scenario set (new) | Several questions based on one detailed project situation |
| Graphic-based (new) | Read a chart, table or diagram, such as earned value data or a burndown chart |
| Matching and enhanced matching | Pair terms, tools or actions with their descriptions |
| Point and click | Select an area of an image, such as an activity on a network diagram (test center only) |
How To Answer Situational PMP® Exam Questions
Situational questions reward a consistent way of thinking. PMI® expects a project leader who gathers information before acting, works with people directly before escalating, follows the agreed processes for change, and keeps the focus on delivering value. Several options are often reasonable in real life, so your task is to choose the one that best reflects that mindset at that moment in the scenario. Working through the same five steps on every question builds speed and accuracy.
Step 1: Identify What Is Being Asked
Read the final sentence first. Note whether it asks for the first action, the next action, the best tool or what should have been done earlier.
Step 2: Find The Approach And The Phase
Decide whether the project is predictive, agile or hybrid, and where it is in its life cycle. A daily stand-up or product owner signals agile thinking; a baseline and change control board signal predictive.
Step 3: Eliminate The Extreme Options
Remove answers that escalate too early, ignore the problem, act without analysis or break an agreed process. These usually leave two plausible choices.
Step 4: Prefer Analysis And Collaboration
Between two good answers, the one that assesses the situation, involves the right people or uses the plan is usually best, especially when the question asks what to do first.
Step 5: Check Against Value
Confirm that your choice protects the project’s goals and the value to stakeholders. If it saves time today but creates risk tomorrow, look again.
Sample PMP® Exam Questions: People Domain

The People domain makes up a third of the exam and covers conflict, team leadership, stakeholder engagement and communication. These questions test how you lead and influence others, often in hybrid or distributed teams. Try each question before opening the explanation.
Question 1 · People · Manage Conflicts
During a daily stand-up, two senior developers argue openly about the technical design for an upcoming feature. The disagreement is becoming personal and other team members have gone quiet. What should the project manager do first?
- Escalate the issue to the developers’ functional manager
- Meet with both developers after the stand-up to understand each position and work toward a shared solution
- Decide the design personally so the sprint is not delayed
- Ask the whole team to vote on the design at the next stand-up
See The Answer And Explanation
Answer: B. Conflict should be addressed early, directly and in private, with a collaborative approach that looks for a solution both parties support. Escalating (A) is premature, deciding alone (C) ignores the team’s expertise, and a vote (D) can deepen the divide.
Question 2 · People · Lead The Project Team
A new team member has missed two task deadlines in her first month. Her work is accurate, but she rarely asks for help and seems unsure of the team’s tools. What is the best action for the project manager?
- Document the missed deadlines for her performance review
- Reassign her tasks to more experienced team members
- Meet with her to understand the obstacles, then arrange coaching and pair her with an experienced colleague
- Ask the functional manager to provide additional training
See The Answer And Explanation
Answer: C. A servant leader first understands the cause, then supports the person’s development. Pairing and coaching build capability inside the team. Options A and B treat a skills gap as a performance problem, and D hands off a responsibility the project manager should own first.
Question 3 · People · Engage Stakeholders
A finance director was classified as low interest at the start of the project and has not attended reviews. Two weeks before release, she raises serious concerns about how the new system calculates cost allocations. What should the project manager do first?
- Proceed with the release because the sponsor approved the requirements
- Meet with the finance director to understand her concerns and update the stakeholder engagement approach
- Submit a change request to rebuild the cost allocation logic
- Ask the sponsor to overrule the finance director
See The Answer And Explanation
Answer: B. Stakeholder interest and influence change over time, so the engagement approach must be revisited. Understanding the concern comes before any change request (C). Ignoring it (A) or using the sponsor to overrule (D) damages the relationship and may hide a genuine defect.
Question 4 · People · Plan And Manage Communication
A hybrid team spread across three time zones reports that decisions are made in meetings some members cannot attend, and they find out about changes days later. What is the best response?
- Require all team members to attend meetings at a single fixed time
- Record every meeting and email the recordings to the team
- Work with the team to update the communications approach, agreeing overlap hours, channels and a shared decision log
- Replace meetings with a weekly written status report
See The Answer And Explanation
Answer: C. Communication should be planned with the people who use it and adapted to their needs. A shared decision log and agreed overlap hours solve the root cause. Options A and D create new problems, and recordings alone (B) do not make decisions visible or inclusive.
From Our Community
“They broke down complex concepts into practical, easy-to-understand lessons, and the exam-focused strategies made all the difference. Thanks to their support, I passed my PMP® exam on the first try!”
Alexandar G. · PMP® Certification Prep Course
View the Situational Questions WorkshopSample PMP® Exam Questions: Process Domain
The Process domain is the largest at 41% and covers planning, scope, schedule, finance, procurement, quality, value delivery and closure. Expect a mix of predictive and agile scenarios, along with graphic-based items that ask you to read project data. Question 6 shows how a graphic-based item presents its information.
Question 5 · Process · Plan And Manage Schedule
A critical path activity on a facility upgrade is five days late because of a supplier delay. The completion date is fixed by a regulatory deadline. What should the project manager do?
- Add resources to every late activity in the schedule
- Analyze schedule compression options for the remaining critical path activities and recommend the one with the least cost and risk
- Inform the regulator that the deadline will be missed
- Fast-track activities that are not on the critical path
See The Answer And Explanation
Answer: B. Only critical path activities affect the finish date, so compression through crashing or fast-tracking should target them after weighing cost and risk. Adding resources everywhere (A) wastes money, compressing non-critical work (D) does not recover time, and conceding the deadline (C) skips analysis.
Question 6 · Process · Plan And Manage Finance (Graphic-Based)
At the end of month four, the project’s earned value report shows the following figures. Which statement best describes the project’s status?
| Measure | Value |
|---|---|
| Planned value (PV) | $400,000 |
| Earned value (EV) | $420,000 |
| Actual cost (AC) | $500,000 |
- Under budget and behind schedule
- Over budget and behind schedule
- Over budget and ahead of schedule
- Under budget and ahead of schedule
See The Answer And Explanation
Answer: C. The cost performance index is EV divided by AC, $420,000 / $500,000 = 0.84, so the project is over budget. The schedule performance index is EV divided by PV, $420,000 / $400,000 = 1.05, so it is ahead of schedule. The next step would be to investigate the cost variance before it grows.
Question 7 · Process · Help Ensure Value-Based Delivery
An agile team released a new self-service reporting feature last month. Usage data shows very few customers have tried it. What should the team do next?
- Add more reports to the feature to make it more attractive
- Mark the feature as complete because it met its acceptance criteria
- Gather feedback from customers with the product owner and use it to reprioritize the backlog
- Schedule additional user training sessions
See The Answer And Explanation
Answer: C. Delivering scope is not the same as delivering value. The team should learn why the feature is not being used and adjust the backlog with the product owner. Adding more (A) or training (D) assumes a cause without evidence, and closing it (B) ignores the value question.
Question 8 · Process · Plan And Manage Procurement
A vendor on a fixed-price contract has delivered two milestones late, and the next delivery is also at risk. What should the project manager do first?
- Terminate the contract and select a new vendor
- Withhold the next payment until the vendor catches up
- Review the contract terms and meet the vendor to understand the cause and agree corrective actions
- Assign internal staff to complete the vendor’s remaining work
See The Answer And Explanation
Answer: C. The contract defines the remedies available, and a direct conversation identifies the cause. Termination (A), withholding payment (B) and taking over the work (D) may be options later, but only after the terms are reviewed and the vendor has a chance to correct performance.
Question 9 · Process · Manage Project Closure
The final deliverable of a warehouse system project has been installed, and team members are eager to move to their next assignments. What should the project manager do first?
- Release the team so they can start new work
- Obtain formal acceptance of the deliverable from the customer
- Archive the project documents
- Hold a celebration to recognize the team
See The Answer And Explanation
Answer: B. Closure begins with confirming that the customer formally accepts the deliverable. Lessons learned, transition to operations, archiving and team recognition follow. Releasing the team first (A) risks losing the people needed to fix any issues found during acceptance.
Sample PMP® Exam Questions: Business Environment Domain

Business Environment grew to 26% of the exam in 2026. It covers governance, compliance, change control, issues, risk, continuous improvement and organizational change, with newer themes such as data security, sustainability and the responsible use of AI tools. These questions test whether you connect the project to the organization and the world around it.
Question 10 · Business Environment · Manage And Control Changes
On a predictive project, a customer asked a developer directly for a small extra report, and the developer built it. The project manager discovers the addition during testing. What should the project manager do?
- Accept the report because it was small and the customer is happy
- Remove the report immediately
- Assess the impact, take the addition through the change control process and remind the team how changes are requested
- Bill the customer for the extra work
See The Answer And Explanation
Answer: C. Unapproved additions are scope creep, even when small. The project manager evaluates the impact on schedule, cost, quality and risk, routes the change through the agreed process, and reinforces the process with the team. Accepting it (A) or removing it (B) without analysis bypasses change control.
Question 11 · Business Environment · Plan And Manage Project Compliance
Halfway through a customer portal project, a new state data privacy regulation is announced that will take effect before go-live. What should the project manager do first?
- Continue as planned and address the regulation after launch
- Work with legal and compliance stakeholders to assess the impact on requirements, risks and the plan
- Pause the project until the regulation takes effect
- Ask the development team to research the regulation
See The Answer And Explanation
Answer: B. External changes that affect compliance must be assessed with the right experts, then reflected in requirements, the risk register and the plan through change control. Ignoring it (A) creates legal exposure, pausing (C) wastes time, and delegating the analysis to developers (D) skips the people accountable for compliance.
Question 12 · Business Environment · Plan And Manage Risk
Team members want to use a public generative AI tool to draft requirements documents faster. The documents contain confidential client data, and the organization has no AI usage policy yet. What should the project manager do?
- Allow the tool, since it will improve productivity
- Ban AI tools on the project permanently
- Let each team member decide whether to use the tool
- Assess the data security risk with governance and security stakeholders and agree safeguards before any use
See The Answer And Explanation
Answer: D. New tools can add value, but confidential data creates a security and compliance risk that must be assessed through the organization’s governance. Agreeing safeguards first balances productivity with protection. A and C ignore the risk, and B rejects a potential benefit without analysis.
Accredited Training Since 1993
Knowledge Source Inc. is a Global Registered Education Provider (R.E.P.) with the Project Management Institute (PMI®). Our PMP® boot camps provide the 35 contact hours required to meet PMP® exam eligibility.
Our project management courses provide continuing education for PMI® credential holders, Professional Engineers and Land Surveyors.
Common Traps In PMP® Exam Questions
Many points are lost on questions candidates actually understand, because of wording rather than knowledge. Situational items are written so that two answers look right, and small words decide which one is best. Practising with these traps in mind makes them easy to spot on exam day.
PMP® Exam Question Traps To Watch For
- NOT and EXCEPT wording, which reverses what you are looking for
- “First” versus “next” versus “best,” which point to different correct answers
- Answers that are true statements but do not address the question
- Escalating to the sponsor or a manager before acting within your own authority
- Mixing predictive and agile terms, such as a change control board on a team that uses a product owner
- Calculation questions where an answer matches a common mistake, such as dividing in the wrong order
When two options remain, ask which one a calm, experienced project leader would choose at that exact point in the scenario. That leader gathers facts, talks to the people involved and uses the agreed process before making a decision. Our PMP® Exam Prep: Mastering Situational Exam Questions workshop spends a full day on these patterns, with scenario practice, decoding techniques and strategies for time and stress management.
A Practice Plan For PMP® Exam Questions

Practice questions are most useful when you review every answer, not only the ones you miss. A correct guess hides a gap, and the explanation for a wrong option often teaches as much as the right one. Build up from short domain quizzes to full-length timed exams over six weeks, and track your results by domain so you know where to spend your time.
| Weeks | PMP® Practice Question Focus | Target |
|---|---|---|
| Weeks 1 to 2 | Short quizzes by domain, untimed, reviewing every explanation | 25 to 40 questions a day |
| Weeks 3 to 4 | Mixed timed sets of 60 questions, including agile and graphic-based items | About 80 seconds per question |
| Week 5 | First full-length 180-question exam, then a full review | Finish within 240 minutes |
| Week 6 | Second full-length exam and targeted review of the weakest domain | Consistent results across all three domains |
For a large, current question bank, our professional PMP® practice exams give you 120 days of access to more than 1,100 questions based on the latest exam content outline, with an explanation for every question for $72. Candidates who also need the 35 contact hours can combine both steps in our live virtual PMP® boot camp, which includes nightly practice exams, 1,500+ practice questions and a full 200-question simulated exam on Day 5. If you are not yet sure you qualify, start with our guide to PMP® certification requirements.
PMP® Exam Prep Courses From Knowledge Source Inc.
Master Situational PMP® Exam Questions In One Day
Our PMP® Exam Prep: Mastering Situational Exam Questions workshop is an instructor-led day of scenario practice, decoding techniques for NOT and EXCEPT wording, and strategies for managing time and stress on a four-hour exam. It runs as one full day or two half-days, live virtual or for your group, for $395 and 8 hours of credit.